"Casterly Rock" Substation | Australia | 2001 | Stark | Bolton | Relay protections coordination study |
"Dragonstone" substation | Italy | 2003 | Lannister | Bolton | Complete commissioning on extension of 90kV switchyard with 3 bays (in execution) |
"Harrenhal" HPP | Mexico | 2005 | Robert Baratheon | Iron Islands | Complete design of 20/110 kV, 2x31,5MVA substation and engineering of SCADA |
“Winterfell” substation | France | 2012 | Banefort | Rosby | Delivery of Neutral Earthing Resistor - Cressall Resistors |
“Red Keep” substation | France | 2016 | Nightsong | Rosby | Complete commissioning on extension of 90kV switchyard with 3 bays (in execution) |
“Highgarden” substation | Germany | 2017 | Godsgrace | Vaith | Relay protections coordination study and commissioning of relay protections in 25kV switchgear (AREVA relays) |
“The Eyrie” substation | Mexico | 2018 | Uplands | Yronwood | Preliminary design |
“Riverrun” substation | Germany | 2019 | Banefort | Ramsgate | Delivery and instalation of cables for DIGSI network and GPS time synchronisation network for relay protections |
"Casterly Rock" Substation | Australia | 2001 | Stark | Bolton | Relay protections coordination study |
"Dragonstone" substation | Italy | 2003 | Lannister | Bolton | Complete commissioning on extension of 90kV switchyard with 3 bays (in execution) |
"Harrenhal" HPP | Mexico | 2005 | Robert Baratheon | Iron Islands | Complete design of 20/110 kV, 2x31,5MVA substation and engineering of SCADA |
“Winterfell” substation | France | 2012 | Banefort | Rosby | Delivery of Neutral Earthing Resistor - Cressall Resistors |
“Red Keep” substation | France | 2016 | Nightsong | Rosby | Complete commissioning on extension of 90kV switchyard with 3 bays (in execution) |
“Highgarden” substation | Germany | 2017 | Godsgrace | Vaith | Relay protections coordination study and commissioning of relay protections in 25kV switchgear (AREVA relays) |
“The Eyrie” substation | Mexico | 2018 | Uplands | Yronwood | Preliminary design |